Showing posts with label Integration Management. Show all posts
Showing posts with label Integration Management. Show all posts

Tuesday, November 27, 2012

Project Integration Management

This chapter covers key concepts related to Project Integration Management.
The knowledge area of Project Integration Management consists of the following seven processes -
Project Integration Processes
ProcessProject PhaseKey Deliverables
Develop Project CharterInitiatingProject Charter
Develop Project Management PlanPlanningProject Management Plan
Direct and Manage Project ExecutionExecutionDeliverables
Monitor and Control Project WorkMonitoring and ControlChange Requests
Perform Integrated Change ControlMonitoring and ControlChange Requests status updates
Close Project or PhaseClosureFinal product
A project charter
  • Formally authorizes the project.
  • Gives the objectives and business case
  • Identifies the Project Manager.
  • Generic enough not to change often.
  • Written by a Manager higher in authority than Project Manager.
  • Includes name, description, deliverables
  • A project does not start unless it has a Project charter.
The Inputs, Tools and Techniques and Output of Develop Project Charter process are given below.
Develop Project Charter process
InputsTools & TechniquesOutputs
Project Statement of workExpert judgmentProject Charter
Business case

Contract

Enterprise environmental factors

Organizational process assets

During project execution the project team focuses on completing the tasks assigned. The Senior Management protects the project from changes and loss of resources. The Project Manager integrates all the pieces into the project as a whole.
The Inputs, Tools and Techniques, and Outputs of the Develop Project Management Plan process are given in the table below.
Develop Project Management Plan process
InputsTools & TechniquesOutputs
Project charterExpert judgmentProject Management Plan
Outputs from planning processes

Enterprise environmental factors

Organizational process assets

At the end of each phase of a project, a lessons learned document must be prepared. The lessons learned document defines what was done right, wrong etc. It is required to be completed in order for the project to be completed.
Project Management Information System (PMIS) is a system that keeps track of status of all the project tasks. It is used to track the status of the project. The exam does not focus on any specific system (for example Microsoft Project ).
Project Management Plan is developed by Project Manager with inputs from the team, stakeholders and management. Project Management Plan development is iterative. A Project Management Plan is bought into, approved, realistic and formal.
A Project Management Plan includes -
  • Project Charter
  • Budget
  • Schedule
  • Resources
  • Scope Statement
  • WBS
  • Responsibility charts/assignments
  • Management Plans
A Project Management Plan consolidates other management plans. These are:
  1. Scope management plan
  2. Requirement management plan
  3. Schedule management plan
  4. Cost management plan
  5. Quality management plan
  6. Process improvement plan
  7. Human resource plan
  8. Communication management plan
  9. Risk management plan
  10. Procurement management plan
The Project Management Plan also includes project baselines. These are:
  1. Schedule baseline
  2. Cost performance baseline
  3. and
  4. Scope baseline
Project baseline refers to the original version of the project management plan. Once the project management plan is baselined, it may only be changed by raising a change request.
Progressive Elaboration involves the process of taking a project from concept to detailed design.
Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders.
Direct and Manage Project Execution process includes performing the work defined in the PMP to achieve project goals. The Input, Tools and Techniques and Outputs of this process are given below.
Direct and Manage Project Execution process
InputsTools & TechniquesOutputs
Project management planExpert judgmentDeliverables
Approved change requestsProject management information systemWork performance information
Enterprise Environmental factors
Change requests
Organizational process assets
Project management plan updates


Project document updates
Monitor and Control project work process includes tracking and reviewing the progress of the project. The Input, Tools and Techniques and Outputs of this process are given below.
Monitor and Control project work process
InputsTools & TechniquesOutputs
Project management planExpert judgmentChange requests
Performance reports
Project management plan updates
Enterprise environmental factors
Project document updates
Organizational process assets

The change requests that get generated are evaluated as part of the Perform Integrated Change Control process. The change requests on the project deliverables and project artifacts are managed in this process. The Input, Tools and Techniques and Outputs of this process are given below.
Perform Integrated Change Control process
InputsTools & TechniquesOutputs
Project management planExpert judgmentChange request status updates
Work performance informationChange control meetingsProject management plan updates
Change requests
Project document updates
Enterprise environmental factors

Organizational process assets

Change Control Board is formed to review change requests. It is used to approve or reject change requests. After the project scope has been baselined, each requested change must go through a change control review process.
Project Manager needs to be proactive in looking for deviations from project plan and then take timely corrective action. After that the Project Manager needs to evaluate the effectiveness of corrective action, and measure performance of corrective action, and then determine the need for further corrective action.
When a change request is received, the following steps must be taken (in this order) -
  1. Evaluate (assess) the impact of change to the project
  2. Create alternatives including cutting other tasks, crashing, fast-tracking etc.
  3. Meet with management, sponsors etc.
  4. Meet with the customer if necessary
The Close Project or Phase is the process of formal completion of all project related activities. The Input, Tools and Techniques and Outputs of this process are given below.
Close Project or Phase
InputsTools & TechniquesOutputs
Project management planExpert judgmentFinal product, service or result transition
Accepted deliverables
Organizational process assets updates
Organizational process assets

At the end of each phase of a project, a lessons learned document must be prepared. The lessons learned document defines what was done right, wrong etc. It is required to be completed in order for the project to be completed.
    Questions on Project Integration Management fundamentals are available in Questions by Topic.
/