Questions on Project Time Management


    perparepm is thankful to Neeraj Kanojia for providing these questions.

  1. Activity Definition is typically performed by which of the following:
    1. Project Manager who created the WBS
    2. Project Team Members responsible for the work package
    3. Project Officer
    4. Project Stakeholder

  2. Which of the following is not an activity attribute:
    1. Person responsible for the activity
    2. Location where to perform the activity
    3. Time when to perform the activity
    4. Leads and Lags

  3. Which of the following does NOT generate changes to the Project documents:
    1. Define Activities
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations

  4. Which of the following may generate a milestone list:
    1. Define Activities
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations

  5. In PDM, which of the following relationships is rarely used:
    1. Finish-to-Start
    2. Start-to-Finish
    3. Start-to-Start
    4. Finish-to-Finish

  6. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
    1. Finish-to-Start
    2. Start-to-Finish
    3. Start-to-Start
    4. Finish-to-Finish

  7. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
    1. ADM
    2. PDM
    3. A dependency with lag
    4. A dependency with lead

  8. The following BEST describes a subnetwork:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Activity-On-Node [AON]

  9. A Project Manager in-charge of a Software Development projects is creating a project schedule network diagram for the code development component of the project. This is an example of:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Activity-On-Node [AON]

  10. What-if scenario analysis is done as a part of which process:
    1. Sequence Activities
    2. Define Activities
    3. Develop Schedule
    4. Control Schedule

  11. AON refers to:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Mandatory Dependencies

  12. AOA refers to:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Mandatory Dependencies

  13. Activity Resource Requirements is an input to which of the following processes:
    1. Estimate Activity Durations
    2. Control Schedule
    3. Estimate Activity Resources
    4. Sequence Activities

  14. Dummy relationships or dummy activities can be used in which of the following Activity Sequencing techniques:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Schedule Network Templates

  15. Which of the following is NOT an input to the Sequence Activities process:
    1. Project Scope Statement
    2. Activity Attributes
    3. Activity List
    4. Change Requests

  16. Which of the following is a technique for Sequence Activities:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Rolling Wave Planning
    4. Mandatory Dependencies

  17. Reserve Analysis is a technique for:
    1. Define Schedule
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations

  18. Resource Leveling is a technique for:
    1. Develop Schedule
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations

  19. Following can be BEST described as a kind of dependency that can create arbitrary float values and limit scheduling options:
    1. Mandatory dependency
    2. Discretionary dependency
    3. Start-to-Finish dependency
    4. External dependency

  20. Critical path method is used in which of the following processes:
    1. Sequence Activities
    2. Define Activities
    3. Develop Schedule
    4. Estimate Activity Durations

  21. Parametric Estimating is done as a part of which process:
    1. Sequence Activities
    2. Develop Schedule
    3. Estimate Activity Resources
    4. Estimate Activity Durations

  22. Identification of Mandatory Dependencies is BEST done during which process:
    1. Sequence Activities
    2. Develop Schedule
    3. Define Activities
    4. Estimate Activity Duration

  23. Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique:
    1. Critical Path Method
    2. Schedule Compression
    3. What-if Analysis
    4. Resource Leveling

  24. Knowledge of best practices in a particular area is MOST likely to give rise to which of the following dependencies:
    1. Finish-to-Start dependency
    2. Soft Logic
    3. Mandatory dependency
    4. External dependency

  25. A Project Manager is preparing a Project Schedule network diagram. During the diagram development, she removes a dependency between two tasks that was defined in an earlier stage. After the network diagram is completed, she updates activity attributes for the two tasks. This is an example of:
    1. Define Activities
    2. Sequence Activities
    3. Develop Schedule
    4. Lack of change control

  26. Reserve Analysis involves:
    1. Estimating by multiplying the quantity of work by productivity rate
    2. Incorporating time buffers into the activity duration estimates
    3. Developing project schedule with contingency reserves as a recognition of the schedule risk
    4. Adding resource reserves to the activity resource estimates

  27. Which of the following is not true for Resource Leveling:
    1. Project schedule is build with resource buffers to prevent schedule slippage
    2. Project’s Critical path may be altered
    3. Resource based scheduling method
    4. Reverse resource allocation scheduling

Answers

  1. Answer: B PMBOK Pg. 134
  2. Answer: C Activity attributes are an input for project schedule development; therefore, the scheduling information is not a part of the activity attribute.
  3. Answer: A. Project document updates is an output to all processes in Project Time Management process area except Define Activities.
  4. Answer: A


  5. Answer: B
  6. Answer: A
  7. Answer: D Note that this dependency can be represented by both ADM and PDM techniques.
  8. Answer: C
  9. Answer: C It is not clear what Activity Sequencing technique is the Project Manager using; however, it is evident that she is developing a schedule network diagram for only part of the project (not the entire project)


  10. Answer: C
  11. Answer: A
  12. Answer: B
  13. Answer: A One of the outputs of Estimate activity resources is Activity Resource Requirements. Sequence Activities establishes logical dependencies between activities. Activity Resource requirements do not play an important role in determining the sequence.
  14. Answer: B


  15. Answer: D Approved Change Requests is not a valid input to Sequence Activities process.
  16. Answer: A
  17. Answer: D
  18. Answer: A
  19. Answer: B


  20. Answer: C
  21. Answer: D
  22. Answer: A
  23. Answer: D


  24. Answer: B Discretionary dependencies often result from best practices. This kind of dependency is also known as Soft Logic, Preferential Logic, or Preferred Logic.
  25. Answer: D The Project manager is preparing the project schedule network diagram which implies she is in the Activity scheduling process. This process can generate changes to the Activity definition and Activity Attributes; however, such changes should go thru the Integrated Change Control and only upon approval should they be made.
  26. Answer: B Answer C might seem more likely, but note the fine difference that Reserve Analysis is purely a technique of determining activity duration, not a schedule development technique.
  27. Answer: A Resource leveling involves creating a resource constrained project schedule.

6 comments:

  1. "Really your post on Project Time Management Project Time Management is really very good and I appreciate it. It’s hard to sort the good from the bad sometimes, but I think you’ve nailed it. You write very well which is amazing. I really impressed by your post.


    "

    ReplyDelete
    Replies
    1. Tag: PM236A51. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

      1. Plan your day using time management techniques

      As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

      If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

      Related post: Free ebook 104 secrets to become a great project manager

      2. Include stakeholders in important project conversations

      While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

      Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

      Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

      3. Regularly communicate with your team

      Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

      For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

      4. Anticipate project setbacks

      Even the best-laid plans often go awry.

      Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

      Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

      Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

      Related post: 92 free project management templates

      5. Stay focused on the details

      A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

      Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

      And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs

      Delete

    2. IEEE Final Year projects Project Center in Chennai are consistently sought after. Final Year Students Projects take a shot at them to improve their aptitudes, while specialists like the enjoyment in interfering with innovation. For experts, it's an alternate ball game through and through. Smaller than expected IEEE Final Year project centers ground for all fragments of CSE & IT engineers hoping to assemble. <Final Year Projects for CSE It gives you tips and rules that is progressively critical to consider while choosing any final year project point.

      JavaScript Training in Chennai

      JavaScript Training in Chennai

      The Angular Training covers a wide range of topics including Components, project projects for cseAngular Directives, Angular Services, Pipes, security fundamentals, Routing, and Angular programmability. The new Angular TRaining will lay the foundation you need to specialise in Single Page Application developer. Angular Training

      Delete
  2. Expected to form you a next to no word to thank you once more with respect to the decent recommendations you've contributed here
    Best Project Management Software

    ReplyDelete
  3. Initial You got a awesome blog .I determination be involved in plus uniform minutes. i view you got truly very functional matters , i determination be always checking your blog blesss. General Contractors in Canada

    ReplyDelete

  4. Thank you for writing such a wonderful blog post. It is really helpful in time management for a small business owner like me.

    ReplyDelete

/