1.
A work breakdown structure numbering system allows the
project team to:
A. Systematically
estimate costs of work breakdown structure elements.
B. Provide
project justification.
C.Identify
the level at which individual elements are found.
2. The
work breakdown structure can BEST be thought of as an effective aid for
_________ communications.
A. Team
B. Project
manager
C.Customer
D. Stakeholder
3.
Which of the following is a KEY output of the Verify
Scope process?
A. A
more complete scope management plan
B. Customer
acceptance of project deliverables
C.Improved
schedule estimates
D. An
improved project management information system
4.
During project executing, a team member comes to the
project manager because he is not sure what work he needs to accomplish on the
project. Which of the following documents contain detailed descriptions of work
packages?
A. WBS
dictionary
B. Activity
list
C.Project
scope statement
D. Scope
management plan
5.
During which part of the project management process is
the project scope statement created?
A. Initiating
B. Planning
C.Executing
D. Monitoring
and controlling
6.
The program was planned years ago, before there was a
massive introduction of new technology. While planning the next project in this
program, the project manager has expanded the scope management plan because, as
a project becomes more complex, the level of uncertainty in the scope:
A. Remains
the same.
B. Decreases.
C.Decreases
then increases.
D. Increases.
7.
During a meeting with some of the project
stakeholders, the project manager is asked to add work to the project scope.
The project manager had access to correspondence about the project before the
project charter was signed and remembers that the project sponsor specifically
denied funding for the scope mentioned by these stakeholders. The BEST thing
for the project manager to do is to:
A. Let
the sponsor know of the stakeholders’ request.
B. Evaluate
the impact of adding the scope.
C.Tell
the stakeholders the scope cannot be added.
D. Add
the work if there is time available in the project schedule.
8.
A new project manager is being mentored by a more
experienced PMP-certified project manager. The new project manager is having
difficulty finding enough time to manage the project because the product and
project scope are being progressively elaborated. The PMP-certified project
manager advises that the basic tools for project management, such as a work
breakdown structure, can be used during project executing to assist the project
manager. For which of the following can a work breakdown structure be used?
A. Communicating
with the customer
B. Showing
calendar dates for each work package
C.Showing
the functional managers for each team member
D. Showing
the business need for the project
9.
During a project team meeting, a team member suggests
an enhancement to the scope that is beyond the scope of the project charter.
The project manager points out that the team needs to concentrate on completing
all the work and only the work required. This is an example of:
A. Change
management process.
B. Scope
management.
C.Quality
analysis.
D. Scope
decomposition.
10.When should the
Verify Scope process be done?
A. At
the end of the project
B. At
the beginning of the project
C. At
the end of each phase of the project
D. During
the planning processes
11.Hie project is mostly
complete. The project has a schedule variance of 300 and a cost variance of
-900. All but one of the quality control inspections have been completed and
all have met the quality requirements. All items in the issue log have been
resolved. Many of the resources have been released. The sponsor is about to
call a meeting to obtain product verification when the customer notifies the
project manager that they want to make a major change to the scope. The project
manager should:
A. Meet
with the project team to determine if this change can be made.
B. Ask
the customer for a description of the change.
C.Explain
that the change cannot be made at this point in the process.
D. Inform
management.
12.You have just joined
the project management office after five years of working on projects. One of
the things you want to introduce to your company is the value of creating and
utilizing work breakdown structures. Some of the project managers are angry
that you are asking them to do “extra work.” Which of the following would be
the BEST thing you could tell the project managers to convince them to use work
breakdown structures?
A. Work
breakdown structures will prevent work from slipping through the cracks.
B. Work
breakdown structures are only needed on large projects.
C.Work
breakdown structures are required only if the project involves contracts.
D. Work
breakdown structures are the only way to identify risks.
13.A new project manager
has asked you for advice on creating a work breakdown structure. After you
explain the process to her, she asks you what software she should use to create
the WBS and what she should do with it when it is completed. You might respond
that it is not the picture that is the most valuable result of creating a WBS.
It is:
A. A
bar chart.
B. Team
buy-in.
C. Activities.
D. A
list of risks.
14.To manage a project
effectively, work should be broken down into small pieces. Which of the
following does NOT describe how far to decompose the work?
A. Until
it has a meaningful conclusion
B. Until
it cannot be logically subdivided further
C. Until
it can be done by one person
D. Until
it can be realistically estimated
15.A project manager may
use ________ to make sure the team members clearly know what work is included
in each of their work packages.
A. The
project scope statement
B. The
product scope
C.The
WBS dictionary
D. The
schedule
16.A project manager has
just been assigned to a new project and has been given the approved project
charter. The FIRST thing the project manager must do is:
A. Create
a project scope statement.
B. Confirm
that all the stakeholders have had input into the scope.
C.Analyze
project risk.
D. Begin
work on a project management plan.
17.The construction
phase of a new software product is near completion. The next phases are testing
and implementation. The project is two weeks ahead of schedule. Which of the
following processes should the project manager be MOST concerned with before
moving on to the final phase?
A. Verify
Scope
B. Perform
Quality Control
C.Report
Performance
D. Control
Costs
18.You are managing a
six-month project and have held bi-weekly meetings with your project
stakeholders. After five-and-a-half months of work, the project is on schedule
and budget, but the stakeholders are not satisfied with the deliverables. This
situation will delay the project completion by one month. The MOST important
process that could have prevented this situation is:
A. Monitor
and Control Risks.
B. Control
Schedule.
C.Define
Scope.
D.
Control Scope.
19.All of the following
are parts of the scope baseline EXCEPT the:
A. Scope
management plan.
B. Project
scope statement.
C.Work
breakdown structure.
D. WBS
dictionary.
20.One of the
stakeholders on the project contacts the project manager to discuss some
additional scope they would like to add to the project. The project manager
asks for details in writing and then works through the Control Scope process.
What should the project manager do NEXT when the evaluation of the requested scope
is complete?
A. Ask
the stakeholder if there are any more changes expected.
B. Complete
integrated change control.
C.Make
sure the impact of the change is understood by the stakeholder.
D. Find
out the root cause of why the scope was not discovered during project planning.
21.During the completion
of project work, the sponsor asks the project manager to report on how the
project is going. In order to prepare the report, the project manager asks all
the team members what percent complete their work is. There is one team member
who has been hard to manage from the beginning. In response to being asked what
percent complete he is, the team member asks, “Percent complete of what?” Being
tired of such comments, the project manager reports to the team members boss that
the team member is not cooperating. Which of the following is MOST likely the
real problem?
A. The
project manager did not get buy-in from the manager for the resources on the
project.
B. The
project manager did not create an adequate reward system for team members to
improve their cooperation.
C.The
project manager should have had a meeting with the team members boss the first
time the team member caused trouble.
D. The
project manager did not assign work packages.
22.The development of
the scope baseline can BEST be described as involving:
A. The
functional managers.
B. The
project team.
C.All
the stakeholders.
D. The
project expediter.
23.Which of the
following is an output of the Collect Requirements process?
A. Requirements
traceability matrix
B. Project
scope statement
C.Work
breakdown structure
D.
Change requests
24.A scope change has
been suggested by one of the stakeholders on the project. After careful
consideration and a lot of arguing, the change control board has decided to
reject the change. What should the project manager do?
A. Support
the stakeholder by asking the board for the reason for the rejection.
B. Suggest
to the stakeholder that the next change they request will be approved.
C.Record
the change request and its result.
D. Advise
the change control board to make sure they create approval processes before the
next change is proposed.
25.The cost performance
index (CPI) on the project is 1.13, and the benefit cost ratio (BCR) is 1.2.
The project scope was created by the team and stakeholders. Requirements on the
project have been changing throughout the project. No matter what the project
manager has tried to accomplish in managing the project, which of the following
is he MOST likely to face in the future?
A. Having
to cut costs on the project and increase benefits
B. Making
sure the customer approved the project scope
C.Not
being able to measure completion of the product of the project
D. Having
to add resources to the project
26.Verify Scope is
closely related to:
A. Perform
Quality Control.
B. Sequence
Activities.
C.Perform
Quality Assurance.
D. Time
Management.
27.Which of the
following can create the MOST misinterpretation of the project scope statement?
A. Imprecise
language
B. Poor
pattern, structure, and chronological order
C.Small
variations in size of work packages or detail of work
D. Too
much detail
28.Which of the
following is CORRECT in regard to the Control Scope process?
A. Effective
scope definition can lead to a more complete project scope statement.
B. The
Control Scope process must be done before scope planning.
C.The
Control Scope process must be integrated with other control processes.
D. Controlling
the schedule is the most effective way of controlling scope.
29.Which of the
following BEST describes the Verify Scope process?
A. It
provides assurances that the deliverable meets the specifications, is an input
to the project management plan, and is an output of Perform Quality Control.
B. It
ensures the deliverable is completed on time, ensures customer acceptance, and
shows the deliverable meets specifications.
C.It
ensures customer acceptance, shows the deliverable meets specifications, and
provides a chance for differences of opinion to come to light.
D. It
is an output of Perform Quality Control, occurs before Define Scope, and
ensures customer acceptance.
30.Which of the
following BEST describes product analysis?
A. Working
with the customer to determine the product description
B. Mathematically
analyzing the quality desired for the project
C.Gaining
a better understanding of the product of the project in order to create the
project scope statement
D.
Determining whether the quality standards on the
project can be met.
ANSWERS
1. Answer
C
Explanation
The
numbering system allows team members to quickly identify the level in the work
breakdown structure where the specific element is found. It also helps to
locate the element in the WBS dictionary
2. Answer
D
Explanation
The
term “stakeholder” encompasses all the other choices. In this case, it is the
best answer since the WBS can be used (but does not need to be used) as a
communications tool for all stakeholders to “see” what is included in the
project.
3. Answer
B
Explanation
The
output of the Verify Scope process is customer acceptance of project
deliverables. The other choices all happen during project planning, well before
the time the Verify Scope process takes place.
4. Answer
A
Explanation
Activity
lists may identify the work package they relate to, but they do not contain
detailed descriptions of the work packages. The project scope statement defines
the project scope, but it does not describe the work a team member is assigned.
The scope management plan describes how scope will be planned, managed, and
controlled. It does not include a description of each work package. The WBS
dictionary defines each element in the WBS. Therefore, descriptions of the work
packages are in the WBS dictionary.
5. Answer
B
Explanation
The
project scope statement is an output of the Define Scope process, which occurs
during project planning.
6. Answer
D
Explanation
Not
all questions will be difficult. The level of uncertainty in scope increases
based on the scale
of effort required to identify all the scope. For larger projects, it is more
difficult to “catch” everything.
7. Answer
C
Explanation
Though
one could let the sponsor know about the stakeholders’ request, the best choice
listed would be to say no. An even better choice would be to find the root
cause of the problem, but that choice is not listed here.
8. Answer
A
Explanation
A
WBS does not show dates or responsibility assignments. The business need is
described in the project charter. In this situation, the product and project
scope are being fine tuned. It would save the project manager time in
effectively managing progressive elaboration if the WBS was used as a
communications tool. Using the WBS helps ensure everyone (including the customer)
understands the scope of the work.
9. Answer
B
Explanation
The
team member is suggesting an enhancement that is outside the scope of the
project charter. Scope management involves focusing on doing the work and only
the work in the project management plan that meets the objectives of the
project charter. The project manager is performing scope management.
10.Answer
C
Explanation
The
Verify Scope process occurs during project monitoring and controlling. It is
done at the end of each
project phase to get approval for phase deliverables, as well as at other
points to get approval for interim deliverables.
11.Answer
B
Explanation
Do
not jump into the problem without thinking. The customer only notified the
project manager that they want to make a change. They did not describe the
change. The project manager should not say no until he or she knows more about
the potential change, nor should the project manager go to management without
more information. The project manager must understand the nature of the change
and have time to evaluate the impact of that change before doing anything else.
Of these choices, the first thing to do is to determine what the change is. The
project manager might then analyze the potential change with the team, but only
if their input is required.
12.Answer
A
Explanation
Work
breakdown structures are required on projects of every size, regardless of
whether contracts are involved. Work breakdown structures can be used to help
identify risks, but risks can be identified using other methods as well.
Preventing work from being forgotten (slipping through the cracks) is one of
the main reasons the tool is used, and is the best choice offered here.
13.Answer
B
Explanation
The
WBS is an input to all of these choices. However, team buy-in is a direct
result of the WBS creation process, while the other choices use the WBS to
assist in their completion. Involving the team in creating the WBS provides
project team members with an understanding of where their pieces fit into the
overall project management plan and gives them an indication of the impact of
their work on the project as a whole.
14.Answer
C
Explanation
The
lowest level of the WBS is a work package, which can be completed by more than
one person. The other choices are aspects of a work package.
15.Answer
C
Explanation
The
project scope statement describes work on a high-level basis. Work packages
need to be specific to enable team members to complete their work without gold
plating. The product scope does not tell team members what work is assigned to
them. The team should have a copy of the schedule, but a schedule does not show
them what work is included in each of their work packages. Work packages are
described in the WBS dictionary. NOTE: Do not think of the WBS dictionary as a
dictionary of terms.
16.Answer
B
Explanation
This
question can be tricky, especially if you have spent so much time studying that
you have forgotten some good project management: practices. A quick look at
Ritas Process Chart in this book might lead you to conclude that the first
thing to do would be to start planning. However, the question indicates that
the project manager was not involved until after the charter was created and
approved. Therefore, wouldn’t it be smart to make sure the project charter is
clear and complete before moving on? This is why it is best for the project
manager to confirm the stakeholders had input into the scope.
17.Answer
A
Explanation The Verify Scope process deals
with acceptance by the customer. Without this acceptance, the project manager
will not be able to move into the next project phase.
18.Answer
C
Explanation Monitor and Control Risks,
Control Schedule, and Control Scope are monitoring and controlling processes.
This situation asks how to prevent the problem, which would have been done
during planning. The project deliverables are defined in the Define Scope
process, which is a part of project planning. Good planning reduces the
likelihood of a situation like the one described, by including the right people
and spending adequate time clarifying the project scope.
19.Answer
A
Explanation The scope baseline includes the
WBS, WBS dictionary, and the project scope statement. The scope management plan
is not part of the scope baseline.
20.Answer
B
Explanation Notice that there are many
things the project manager could do listed in the choices. The question asks
what is the BEST thing to do NEXT. Management of the change is not complete
when the Control Scope process is completed. It is important to look at the
impact of the change on other parts of the project, such as time and cost.
Therefore, performing integrated change control is the best thing to do next.
This would probably be followed by making sure the impact of the change is
understood by the stakeholder, then determining why this scope was not
identified in planning, and asking the stakeholder if there are more changes
expected.
21.Answer
D
Explanation The project manager is not losing
resources (which is implied by not getting the managers buy-in). Although a
reward system would help with cooperation, the real problem here is not
cooperation. Meeting with the team member and his boss cannot be the answer
because it also does not solve the problem at hand (the team member not knowing
what he is to do).
If
you selected this choice, be very careful! You can get 10 to 20 questions wrong
on the exam simply because you do not see the real problem! The whole
discussion of the team member and his actions is a distracter. The real problem
in this scenario is not that the team member is being uncooperative. He is
asking a question that many team members want to ask in the real world. “How
can I tell you how things are going if I do not know what work I am being asked
to do?” The real problem is the lack of a WBS and work packages. If there were
a WBS and work packages for the project, the team member would not have to ask
such a question.
22.Answer
B
Explanation After obtaining input from the
customer and other stakeholders, the project team is responsible for developing
the scope baseline. Remember that the scope baseline includes the WBS, WBS
dictionary, and project scope statement.
23.Answer
A
Explanation The project scope statement is an
output of the Define Scope process. The work breakdown structure is an output
of the Create WBS process. Scope change requests are outputs of the Verify
Scope and Control Scope processes. The requirements traceability matrix is an
output of the Collect Requirements process, and is used to track the
requirements throughout the life of the project.
24.Answer
C
Explanation There is no reason to think that
the board’s rejection would not contain an explanation already, since providing
that information is commonly done. Suggesting a change
process
that circumvents the change control boards authority is not ethical. There is
no reason to think that approval processes are not already in place. A rejected
change should be recorded for historical purposes, in case the idea is
resurrected later, and for other reasons.
25.Answer
C
Explanation
There
are many pieces of data in this question that are distracters from the real
issue. Though it is common to have to cut costs and add resources to a project,
nothing in the question should lead you to think these will be required in this
situation. Customers do not generally approve the project scope (what you are
going to do to complete their requirements); instead, they approve the product
scope (their requirements). Since requirements are used to measure the completion
of the product of the project, not having complete requirements will make such
measurement impossible.
26.Answer
A
Explanation
Perform
Quality Control checks for correctness, and Verify Scope checks for acceptance.
27.Answer
A
Explanation
Much
of the work on the project is dictated by the project scope statement. Any
imprecision in such a key document will lead to differing interpretations.
28.Answer
C
Explanation
Though
it is correct that effective scope definition can lead to a more complete
project scope statement, this cannot be the answer, because it does not deal
with control. Scope planning occurs before the Control Scope process, not after
it. Controlling the schedule is not the best way to control scope, so that is
not the best answer. The control processes do not act in isolation. A change to
one will most likely affect the others. Therefore the need to integrate the
Scope Control process with other control processes is the best answer.
29.Answer
C
Explanation
The
project management plan is completed before the Verify Scope process. The
Verify Scope process does not deal with time, but rather acceptance. The Verify
Scope process does not occur before the Define Scope process. The choice
stating that the Verify Scope process ensures customer acceptance, shows the
deliverable meets specifications, and provides a chance for differences of
opinion to come to light is entirely correct, making that the best answer.
30.Answer
C
Explanation
You
need to have a product description before you can do product analysis.
Analyzing the level of quality desired is related to the Plan Quality process.
Determining whether the quality standards on the project can be met is done in
the Perform Quality Assurance process. Product analysis includes gaining a
better understanding of the product of the project, in order to create the
project scope statement.
scope managementProcesses required to define what work is required and ensure that the project includes only that work required to complete the project. Involves managing both product scope and project scope. Processes outlined are used to manager the project scope only.
ReplyDelete