Tuesday, November 27, 2012

Project Integration Management

This chapter covers key concepts related to Project Integration Management.
The knowledge area of Project Integration Management consists of the following seven processes -
Project Integration Processes
ProcessProject PhaseKey Deliverables
Develop Project CharterInitiatingProject Charter
Develop Project Management PlanPlanningProject Management Plan
Direct and Manage Project ExecutionExecutionDeliverables
Monitor and Control Project WorkMonitoring and ControlChange Requests
Perform Integrated Change ControlMonitoring and ControlChange Requests status updates
Close Project or PhaseClosureFinal product
A project charter
  • Formally authorizes the project.
  • Gives the objectives and business case
  • Identifies the Project Manager.
  • Generic enough not to change often.
  • Written by a Manager higher in authority than Project Manager.
  • Includes name, description, deliverables
  • A project does not start unless it has a Project charter.
The Inputs, Tools and Techniques and Output of Develop Project Charter process are given below.
Develop Project Charter process
InputsTools & TechniquesOutputs
Project Statement of workExpert judgmentProject Charter
Business case

Contract

Enterprise environmental factors

Organizational process assets

During project execution the project team focuses on completing the tasks assigned. The Senior Management protects the project from changes and loss of resources. The Project Manager integrates all the pieces into the project as a whole.
The Inputs, Tools and Techniques, and Outputs of the Develop Project Management Plan process are given in the table below.
Develop Project Management Plan process
InputsTools & TechniquesOutputs
Project charterExpert judgmentProject Management Plan
Outputs from planning processes

Enterprise environmental factors

Organizational process assets

At the end of each phase of a project, a lessons learned document must be prepared. The lessons learned document defines what was done right, wrong etc. It is required to be completed in order for the project to be completed.
Project Management Information System (PMIS) is a system that keeps track of status of all the project tasks. It is used to track the status of the project. The exam does not focus on any specific system (for example Microsoft Project ).
Project Management Plan is developed by Project Manager with inputs from the team, stakeholders and management. Project Management Plan development is iterative. A Project Management Plan is bought into, approved, realistic and formal.
A Project Management Plan includes -
  • Project Charter
  • Budget
  • Schedule
  • Resources
  • Scope Statement
  • WBS
  • Responsibility charts/assignments
  • Management Plans
A Project Management Plan consolidates other management plans. These are:
  1. Scope management plan
  2. Requirement management plan
  3. Schedule management plan
  4. Cost management plan
  5. Quality management plan
  6. Process improvement plan
  7. Human resource plan
  8. Communication management plan
  9. Risk management plan
  10. Procurement management plan
The Project Management Plan also includes project baselines. These are:
  1. Schedule baseline
  2. Cost performance baseline
  3. and
  4. Scope baseline
Project baseline refers to the original version of the project management plan. Once the project management plan is baselined, it may only be changed by raising a change request.
Progressive Elaboration involves the process of taking a project from concept to detailed design.
Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders.
Direct and Manage Project Execution process includes performing the work defined in the PMP to achieve project goals. The Input, Tools and Techniques and Outputs of this process are given below.
Direct and Manage Project Execution process
InputsTools & TechniquesOutputs
Project management planExpert judgmentDeliverables
Approved change requestsProject management information systemWork performance information
Enterprise Environmental factors
Change requests
Organizational process assets
Project management plan updates


Project document updates
Monitor and Control project work process includes tracking and reviewing the progress of the project. The Input, Tools and Techniques and Outputs of this process are given below.
Monitor and Control project work process
InputsTools & TechniquesOutputs
Project management planExpert judgmentChange requests
Performance reports
Project management plan updates
Enterprise environmental factors
Project document updates
Organizational process assets

The change requests that get generated are evaluated as part of the Perform Integrated Change Control process. The change requests on the project deliverables and project artifacts are managed in this process. The Input, Tools and Techniques and Outputs of this process are given below.
Perform Integrated Change Control process
InputsTools & TechniquesOutputs
Project management planExpert judgmentChange request status updates
Work performance informationChange control meetingsProject management plan updates
Change requests
Project document updates
Enterprise environmental factors

Organizational process assets

Change Control Board is formed to review change requests. It is used to approve or reject change requests. After the project scope has been baselined, each requested change must go through a change control review process.
Project Manager needs to be proactive in looking for deviations from project plan and then take timely corrective action. After that the Project Manager needs to evaluate the effectiveness of corrective action, and measure performance of corrective action, and then determine the need for further corrective action.
When a change request is received, the following steps must be taken (in this order) -
  1. Evaluate (assess) the impact of change to the project
  2. Create alternatives including cutting other tasks, crashing, fast-tracking etc.
  3. Meet with management, sponsors etc.
  4. Meet with the customer if necessary
The Close Project or Phase is the process of formal completion of all project related activities. The Input, Tools and Techniques and Outputs of this process are given below.
Close Project or Phase
InputsTools & TechniquesOutputs
Project management planExpert judgmentFinal product, service or result transition
Accepted deliverables
Organizational process assets updates
Organizational process assets

At the end of each phase of a project, a lessons learned document must be prepared. The lessons learned document defines what was done right, wrong etc. It is required to be completed in order for the project to be completed.
    Questions on Project Integration Management fundamentals are available in Questions by Topic.

2 comments:

  1. "Hi There,

    Very Nice post on PMP Notes.That was very helpfull.keep posting"

    ReplyDelete
    Replies

    1. Tag: PM204A54. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

      1. Plan your day using time management techniques

      As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

      If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

      Related post: Free ebook 104 secrets to become a great project manager

      2. Include stakeholders in important project conversations

      While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

      Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

      Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

      3. Regularly communicate with your team

      Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

      For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

      4. Anticipate project setbacks

      Even the best-laid plans often go awry.

      Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

      Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

      Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

      Related post: 92 free project management templates

      5. Stay focused on the details

      A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

      Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

      And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs


      Delete

/