Questions on Project Scope Management

    perparepm is thankful to Neeraj Kanojia for providing these questions. 

  1. Completion of a product scope is measured against:
    1. Product Management Plan
    2. Project Management Plan
    3. WBS & WBS Dictionary
    4. Product Requirements

  2. All of the below are inputs to Define Scope process EXCEPT:
    1. Project Charter
    2. Requirements Document
    3. Organizational process assets
    4. Project Management Plan

  3. Validated deliverables is an input to which of the following processes?
    1. Collect Requirements
    2. Define Scope
    3. Create WBS
    4. Verify Scope

  4. Project Charter is an input to all of the following processes EXCEPT:
    1. Collect requirements
    2. Define Scope
    3. Create WBS
    4. Develop Project Management Plan

  5. Work Performance Measurement is an output of which process:
    1. Define Scope
    2. Create WBS
    3. Verify Scope
    4. Control Scope

  6. If the project is terminated early, the level and extent of completion should be documented. This is done as a part of:
    1. Define Scope
    2. Create WBS
    3. Verify Scope
    4. Control Scope

  7. Verify Scope can be BEST described as the process of
    1. Verifying that the project quality requirements have been met
    2. Obtaining stakeholder's formal acceptance of the project deliverables
    3. Controlling changes to the scope of the project
    4. Verifying that all of the project's objectives have been met

  8. Which of the following can be BEST described as a characteristic of Work Package?
    1. May or may not be cost estimated
    2. Can be scheduled
    3. Can be further decomposed into work packages
    4. May be monitored subject to nature of the project

Answers

  1. C.
  2. D.
  3. D. Validated Deliverables are output of Perform Quality Control process and acts as inputs to Verify Scope process.
  4. C. Project Charter is input to all these processes except Create WBS.


  5. D. Work performance measurement is an output of Control Scope
  6. C
  7. B. Verify Scope is the process of obtaining the stakeholders' formal acceptance of the completed project scope and associated deliverables. [PMBOK Pg. 123]

  8. B. Work Package is the lowest level in the WBS, and is the point, at which it can be reliably scheduled, cost estimated, monitored and controlled.

3 comments:


  1. Tag: PM204A55. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

    1. Plan your day using time management techniques

    As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

    If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

    Related post: Free ebook 104 secrets to become a great project manager

    2. Include stakeholders in important project conversations

    While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

    Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

    Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

    3. Regularly communicate with your team

    Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

    For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

    4. Anticipate project setbacks

    Even the best-laid plans often go awry.

    Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

    Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

    Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

    Related post: 92 free project management templates

    5. Stay focused on the details

    A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

    Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

    And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs


    ReplyDelete

  2. IEEE Final Year projects Project Center in Chennai are consistently sought after. Final Year Students Projects take a shot at them to improve their aptitudes, while specialists like the enjoyment in interfering with innovation. For experts, it's an alternate ball game through and through. Smaller than expected IEEE Final Year project centers ground for all fragments of CSE & IT engineers hoping to assemble. <Final Year Projects for CSE It gives you tips and rules that is progressively critical to consider while choosing any final year project point.

    JavaScript Training in Chennai

    JavaScript Training in Chennai

    The Angular Training covers a wide range of topics including Components, project projects for cseAngular Directives, Angular Services, Pipes, security fundamentals, Routing, and Angular programmability. The new Angular TRaining will lay the foundation you need to specialise in Single Page Application developer. Angular Training

    ReplyDelete
  3. Awesome dispatch! I am indeed getting apt to over this info, is truly neighborly my buddy. Likewise fantastic blog here among many of the costly info you acquire. Reserve up the beneficial process you are doing here. Quality Management Services

    ReplyDelete

/